In the Phase-I of Congo (King) Comika Copper Mine project of Wanbao Mining, its service period is 8 years and total mining and stripping amount is about 60 million tons. Mining and stripping of phase-I project, including perforation, charging, blasting, shoveling and transportation, are jointly assumed by North Blasting Technology Co., Ltd. and local partners. The project is started in early 2015.
Up to October with the rains, all members of Congo (King) project department had completed 135% of annual production task assigned by the owner in only six months, 164% of the quantities of south-I ore bodies in the infrastructure construction period as agreed in the Contract, and over-fulfilled annual tasks in 2015 in advance, which had been highly recognized by the owner, local mining department, government department and safety department for many time. Up to the end of 2015, they had realized accumulative blasting volume of 2.9 million cubic meters, exceeding the task by 1 million cubic meters. By virtue of signing, becoming effective and generating economic benefits in the same year, it has set a record for other project departments of the Company at home and abroad.
Specific to special climate conditions in Congo (King), i.e. project department can only construct in half year, i.e. dry season, project department comprehensively plans and focuses on progress and achievement of blasting volume in the early stage, and over-fulfills annual tasks by overcoming difficulties, such as inadequate personnel, rampant diseases, arduous conditions and shortage of materials. When the rainy season comes in the later stage, project department continues to construct by using water-resistant emulsion explosive, improves the rules and regulations and strictly manages the site, implementation of responsibilities, and internal affairs with an aim of ensuring safe production when there aren’t many blasting tasks, so as to scientifically ensure construction and internal construction at the same time.